Title |
Training
for the national television broadcasting system
|
| |
Approval
date
|
1994
|
| |
Total
budget
$ |
54,500
|
| |
Budget
code
|
PDC/15
URT/01 352 URT 51
|
| |
Source |
IPDC
|
| |
Objectives |
To
provide technical and production-related training.
To provide training in TV news reporting and production of TV news bulletins.
|
| |
Activities |
First
batch of equipment for television production provided.
|
| |
Funds
obligated |
49,500
|
| |
Implementation
rate
& Remarks |
90%.
Arrangements being made for training of editorial and production staff.
|
| |
Project
officers
|
DUPONT
and AZNAR
|
| |
|
|
| |
Title |
Enhancing
the capacity of Tanzanian Information Service.
|
| |
Approval
date
|
1995
|
| |
Total
budget
$ |
758,057
|
| |
Budget
code
|
URT
90 013
|
| |
Source |
UNDP
|
| |
Objectives |
To
train communication staff of TIS.
To provide audio-visual equipment.
|
| |
Activities |
Equipment
provided. Training activities carried out. A seminar for Tanzanian journalists
on the Role of the Media in Development organised.
|
| |
Funds
obligated |
755,057
|
| |
Implementation
rate
& Remarks |
99.6%.Project
completed.
Final report being prepared; project to be financially closed.
|
| |
Project
officers
|
DUPONT
|
| |
|
|
| |
Title |
Rehabilitation
and extension of the rural press project
|
| |
Approval
date
|
1997
|
| |
Total
budget
$ |
45,000
|
| |
Budget
code
|
PDC/18
URT/01 352 URT 81
|
| |
Source |
IPDC
|
| |
Objectives |
To
enhance and consolidate an effective communication network in rural
communities. To improve the printing capacity of the rural press project.
To train and retrain technical, sales, journalistic and production staff
of the rural press.
|
| |
Activities |
|
| |
Funds
obligated |
|
| |
Implementation
rate
& Remarks |
Project approved, December 1997. Project funds allotted in October 1998.
Arrangements being made for implementation.
|
| |
Project
officers
|
AZNAR