Title |
Publishing equipment
for the Yemen Journalists Association
|
| |
Approval
date |
1994
|
| |
Total
budget $ |
70,000
|
| |
Budget
code |
PDC/15 YEM/01 352
YEM 51
|
| |
Source |
IPDC
|
| |
Objectives |
To install a desk-top-publishing
network for journalists and to offer the necessary training.
|
| |
Activities |
Purchase of equipment
and provision of relevant training
|
| |
Funds
obligated |
65,000
|
| |
Implementation
rate
& Remarks |
92%.Equipment has
been delivered to project site. Training courses organised. o Evaluation
pending.
|
| |
Project
officers |
Kaliwo
and Hadlow
|
| |
|
|
| |
Title
|
Computerisation
of the Yemen News Agency
|
| |
Approval
date
|
1996
|
| |
Total
budget $
|
65,000
|
| |
Budget
code
|
PDC/16YEM/01 352
YEM 61
|
| |
Source
|
IPDC
|
| |
Objectives
|
To upgrade the
computer equipment at the SABA News Agency.
|
| |
Activities
|
Purchase of equipment
and provision of relevant training.
|
| |
Funds
obligated
|
63,000
|
| |
Implementation
rate
& Remarks
|
96%. Equipment
has been ordered and is being delivered to project site. Relevant training
course will be conducted once equipment has been installed.
|
| |
Project
officers
|
Kaliwo
|
| |
|
|
| |
Title
|
Computerisation
of the Ministry of Information documentation centres
|
| |
Approval
date
|
1997
|
| |
Total
budget $
|
60,000
|
| |
Budget
code
|
PDC/17 YEM/01 352
YEM 71
|
| |
Source
|
IPDC
|
| |
Objectives
|
Purchase of equipment
and the provision of relevant training courses.
|
| |
Activities
|
|
| |
Funds
obligated
|
10,000
|
| |
Implementation
rate
& Remarks
|
16%. Consultants
have just prepared a master plan of the project. o Awaiting for comments
by the government.
|
| |
Project
officers
|
Kaliwo
|
| |
|