Cambodia Communication
Institute (CCI) Phase II Ministry of Information
|
| |
Approval
date
|
1997 1999
|
| |
Total
budget
$
|
467,797
|
| |
Budget
code
|
510 CMB 61
|
| |
Source
|
FIT Denmark
|
| |
Objectives
|
To Develop a strong,
versatile team of Cambodian trainers backed by a team of local resource
people.
To develop and implement a series of complementary course modules in
journalism training which can be used as a core for a long-term journalism
training course.
To establish an efficient organisational structure for the Institute
capable of being run by Cambodian personnel by mid 1998.
To mobilise supplementary funds to ensure continuous Government fund
allocations for the long term financial sustainability of the of the
Institute and its activities.
To integrate training of Cambodia media professionals in the framework
of the National Higher Education plan.
|
| |
Activities
|
Nearly 600 people
in media and associated fields were trained through 46 training courses
held in 1997. Two training of trainers courses were conducted for the
local training staff CTA was replaced with a local professional officer.
Two International consultancies were fielded to support the local project
staff in their efforts to develop the institutional and training management.
17 training courses of which 6 on election reporting, were conducted
during January-June.
|
| |
Funds
obligated
|
291,441
|
| |
Implementation
rate
&
Remarks |
46%. Phase II project
commenced in January 1997.
The Institutional development of the CCI has been delayed due to the
difficult political situation in Cambodia.
|
| |
Project
officers
|
BENTLEY
and JAYAWEERA
|
| |
|
| |
Title |
Informatization
of Economic Department of the Law Faculty in Phnom Penh
|
| |
Approval
date |
1998
|
| |
Total
budget
$ |
60,000
|
| |
Budget
code |
450 CMB 11
|
| |
Source |
IIP and FIT France
|
| |
Objectives |
To introduce computer
technology at the University.
|
| |
Activities |
Provision of equipment,
training, and expertise.
|
| |
Funds
obligated |
60,000
|
| |
Implementation
rate
&
Remarks |
100%. Contract
established with AFDET/France in August 1997.
Project in progress.
|
| |
Project
officers
|
Kim
|
| |