Increase public
awareness and participation for development. Link isolated communities
with national main stream activities.
Activities
Acquisition of
portable equipment. Training. Evaluation. Post facto evaluation
Funds
obligated
26,897
Implementation
rate & Remarks
100%. 90% upgrade
of the national coverage of the FM station carried out.
Equipment purchased, delivered and installed 23/04/97.
Training to be carried out by GBC, report expected.
Delay due to demise of Manager GBC - late 1997.