Title |
Establishment
of a Community Broadcasting Service at Iwokrama
|
| |
Approval
date
|
1996 - 1997
|
| |
Total
budget
|
US $ equiv. of
CAD 23,520
|
| |
Budget
code
|
525 GUY 60
|
| |
Source
|
FIT: IDRC (Canada)
|
| |
Objectives
|
To stimulate overall development of the Iwokrama District in conjunction
with that of the Iwokrama Rainforest Programme. Provide a medium for
2 way access of information between the interior and the coast. Foster
economic and social upliftment through self-involvement and participation
in community/nation building.
|
| |
Activities
|
Establish a mutually agreed workplan with the national authorities of
Guyana. Identify a local coordinator/trainer and determine choice of
trainees; organize on-site technical and operational training. Procure
and install equipment and materials and prepare contract for execution
of project. Project proposal for further community media development
with appropriate partners for extra-budgetary funding.
|
| |
Funds
obligated
|
12,814
|
| |
Implementation
rate
&
Remarks |
88%.Received written word from Iwokrama Secretariat. Implementation
in October 1997 with technical study by Ron Case.
Report expected. o Indications being thought on first batch of equipment
October 1997.
Delay due to Civil unrest in Guyana.
|
| |
Project
officers
|
Josiah
and Gonzalez
|
| |
|
| |
Title |
Training for
rehabilitation of media
|
| |
Approval
date |
1997
|
| |
Total
budget
|
55,000
|
| |
Budget
code |
PDC/17 GUY/01 352
GUY 71
|
| |
Source |
IPDC
|
| |
Objectives |
Optimize the contribution of journalists and media professionals to
the education and development process. Increase levels of literacy and
awareness of national development issues. Reinforce the existing infrastructure
for media training in production to lead to permanent production capacity
in the country.
|
| |
Activities |
Acquisition and installation of training equipment. Training. Production
and distribution of media materials. Audience evaluation and feedback.
Post-facto evaluation.
|
| |
Funds
obligated |
|
| |
Implementation
rate
&
Remarks |
Allotment received November 1997. Delay due to civil unrest in Guyana.
|
| |
Project
officers
|
Josiah
and Gonzalez
|
| |